Ike Repairs
- Café on the Court has been renovated for temporary use and is now open daily.
- Neonatal Intensive Care Unit (NICU) and Labor & Delivery Nursery are currently being renovated. Design phase: March-June 2009. Construction phase: July-October 2009.

- Elevators—design for repair, mitigation, and modernization is underway. Anticipated scheduled—Design phase: Jan.-Dec. 2009. Construction phase: Jan. 2010-Dec. 2011.

Labor & Delivery Renovation
- Renovations will begin in November for delivery, observation, triage, recovery, and support areas. Design phase: Aug. 2008-Sept. 2009. Construction phase: Nov. 2009-May 2011.