1700 The Strand
BUILDING 39
Ike Repairs
- Repair to damaged masonry and mechanical distribution
equipment. Design schedule: Nov. 2009-Aug. 2010.
Construction schedule: Nov. 2010-Apr. 2012.

Construction Projects
- Building envelope repairs; site improvements including
accessibility and landscaping; new accessible toilet rooms;
some interior remodeling; new accessible passenger elevator;
and, energy performance improvements. Design schedule: Nov.
2009-Aug. 2010. Construction schedule: Nov. 2010-Apr. 2012.

- Elevators—No construction schedule at this time.