Building No.: 71 Map Location: A8
Repairs/equipment relocation - TBD
Building No.: 73 Map Location: A8
Building No.: 87 Map Location: A10
Interior reconstruction - 6/2011-TBD Imaging - 8-9/2012
Mitigation schedule - 3/2012-9/2013
Building No.: 16 Map Location: B7
Building No.: 94 Map Location: B5
Building No.: 21 Map Location: B9
Elevators - complete
Building No.: 64 Map Location: B6
Heat/Crash Room schedule - 12/2011-10/2012
Building No.: 27 Map Location: C9
Demolition is complete.
Building No.: 31 Map Location: C10
Project repairs completed.
Building No.: 35 Map Location: C11
Construction schedule: TBD
Building No.: 17 Map Location: C4
Freight elevator - TBD
Building No.: 1 Map Location: C6
Mitigation - 7-2012-5/2013
Window repair schedule - 10/2012-4/2013
Building No.: 19 Map Location: C5
Ground floor mitigation repairs - TBD
Building No.: 14 Map Location: C5
Construction complete.
Building No.: 30 Map Location: C10
Elevators—complete.
Building No.: 32 Map Location: C10
Building No.: 34 Map Location: C11
Construction schedule - HOLD
Building No.: 4 Map Location: C5
Building No.: 56 Map Location: C6
Entry, Lobby & Concourse Renovation - 8/2012-7/2013
Surgical Simulation Center - 4-9/2013
Building No.: 11 Map Location: C7
Fire sprinkler repairs - 1-12/2013
Switchgear mitigation - 10/2012-9/2013
Concourse - 8/2012-7/2013
Building No.: 2 Map Location: D6
Mitigation - TBD
Freight Elevator - TBD
Elevator - TBD
Building No.: 9 Map Location: D7
Roof replacement - 8-12/2012
Concourse - 10/2012-7/2013
Building No.: 47 Map Location: D8
Roof replacement - 10/2012-12/2013
Building No.: 59 Map Location: D5
Elevator Phase III construction schedule - 3-7/2012
Building No.: 57 Map Location: D4
Second Floor Offices - 12/2011-3/2012
Building No.: 28 Map Location: D2
Elevator schedule - 7/2012-2/2013
Building No.: 54 Map Location: D5
Mitigation schedule - TBD
Irradiator/Fire Command Center schedule - 3-11/2012
5th Floor renovation schedule - 11/2011-10/2012
Building No.: 95 Map Location: D2
Construction schedule - 6-10/2012
Building No.: 93 Map Location: D3
Elevator construction schedule - TBD
Building No.: 7 Map Location: D7
Public Concourse renovation schedule - 9/2012-7/2013
Building No.: 37 Map Location: D9
Repairs construction schedule - TBD
Building No.: 41 Map Location: D6
A/C Stairwell & Pressurization Rooms - 10/2012-1/2013
Building No.: 75 Map Location: D11
Building No.: 90 Map Location: D7
Entry, Lobby & Concourse renovation schedule - 8/2012-7/2013
Elevator Modernization/Phase VIII schedule - 6-10/2012
Infrastructure, L2 - 5/2010-11/2012
Building No.: 12 Map Location: D8
Renovation Phase I - 5/2012-1/2013
Building No.: 6 Map Location: E7
Structural Biology renovation, Phase II - 10/2012-3/2013
Building No.: 55 Map Location: E5
Ground Floor minor repairs - TBD
Building No.: 69 Map Location: E8
Elevator schedule - TBD
Building No.: 24 Map Location: E6
Restore ground floor of library - 6/2012-4/2013
Glazing project - 6/2012-4/2013
Library facilities upgrades - 6/2012-4/2013
Building No.: 67 Map Location: E3
Repairs complete.
Building No.: 77 Map Location: E11
Repair schedule - 9/2012-1/2013
Building No.: 49 Map Location: E2
Project repairs schedule - 7-12/2012
Building No.: 70 Map Location: F5
Repair & mitigation schedule - 5-10/2012
Building No.: 121 Map Location: F8
Ground floor/corridor - 1-8/2012
Building No.: 141 Map Location: F8