After a successful run that spanned five decades, the final Impact was published in January 2020.  Impact was UTMB Health’s employee newsletter. It evolved from a one color printed tabloid newspaper to a full color magazine with a digital component. We’ve archived the past several years on these pages for your review and enjoyment.

utmbnewslettertab

Impact is for and about the people who fulfill UTMB’s mission to improve health in Texas and around the world. We hope you enjoy reading this issue. Let us know what you think!

John Sealy Hospital Modernization

Construction Update

Jun 20, 2017, 06:13 AM by Stephen Hadley


UTMB’s three campuses continue to experience growth and expansion. The following are some of the projects currently underway at the institution:

Invasive Cardiology Services
Location: Jennie Sealy Hospital
Project Scope: Cath labs, Electrophysiology labs and Post-Anesthesia Care Unit will be located on 6th Floor of Jennie Sealy Hospital, with support offices on 6th Floor of Clinical Services Wing.
Timeline: Construction to start in August; operational in October 2018

John Sealy Hospital Modernization John Sealy Hospital Modernization (facade)
Project Scope: Updating facade to more closely mirror look of Jennie Sealy Hospital
Status: Mechanical scaffolding completed on north and east sides; installation underway on south side. Exterior mockup under construction at lot on Harborside Drive with moisture testing set for July.
Timeline: Operational by 2020


MD Anderson Cancer Center at UTMB League City Campusmdacc_lc

Project Scope: Four-story cancer treatment center
Status: Fourth-floor slab complete with roofing installation ongoing
Timeline: Substantial completion for Levels 1, 3 and 4 set for Spring 2018; Level 2 substantial completion set for Summer 2018